Technology · News
Microsoft exits Nscale's flagship Essex AI datacentre deal over UK grid delays
Published:

In brief
Microsoft has withdrawn as anchor tenant from a planned £2 billion AI datacentre that British firm Nscale is building in Loughton, Essex, after UK Power Networks said it could not connect the site to the grid until the early-to-mid 2030s. Nscale says it remains committed to Loughton and is looking at alternative power sources, including on-site generation, while pursuing a planned stock market listing.
Microsoft has pulled out of its agreement to be the anchor tenant at a planned AI datacentre in Loughton, Essex, being developed by British infrastructure company Nscale, according to reports first published by The Daily Telegraph and confirmed by other outlets on 18 October 2026.
The site had been promoted by Nscale and government figures as set to become one of the largest AI computing facilities in the UK when it was unveiled in September 2025, as part of a wider package of AI infrastructure announcements involving Microsoft and Nvidia.
Why Microsoft withdrew
The decision centres on electricity supply. UK Power Networks, the regional grid operator, told Nscale it would not be able to deliver sufficient power to the Loughton site until the early-to-mid 2030s, well beyond the facility's planned 2027 opening. The delay would have left Microsoft's planned computing hardware deployment stranded for years.
Nscale said in a statement that it remains committed to the site. "We remain committed to both the Loughton project and the UK, and we are exploring alternative power sources for the site, in addition to other expansion sites in the UK," a company spokesperson said. The company added separately that the issue reflects a broader London-area grid constraint and that its relationship with Microsoft on other contracts, including a facility in Norway, is unaffected.
Nscale is reported to be examining on-site power generation as a workaround, including discussions with Bloom Energy, a California-based maker of solid-oxide fuel cells that generate electricity from natural gas. Bloom Energy has not commented publicly on the reports.
The project's path so far
Epping Forest District Council approved planning permission for the Loughton site despite objections from the local town council and its own landscape and urban design teams, who raised concerns about water and power demand. Council officers cited a letter from Lord Stockwood, the UK's Minister for Investment, who had described the project as important to the "UK-US technological partnership" and said the government was "keen to see the successful delivery of this site."
What is confirmed and what is not
| Metric | Announced (Sept 2025) | Status (Oct 2026) |
|---|---|---|
| Anchor tenant | Microsoft | No replacement announced |
| Site investment | £2 billion (Nscale) | Unchanged, per Nscale |
| Grid connection target | In time for opening | Not before early/mid-2030s, per UK Power Networks |
| Planned opening | 2027 | Delayed; new timeline not confirmed |
| Scalable capacity | Up to 90 megawatts | Unchanged on paper |
Figures for the number of computing chips planned for the site vary between outlets and have not been confirmed by Microsoft or Nscale directly in on-the-record statements reviewed for this piece; this detail is therefore not stated as fact here.
Wider context
The withdrawal comes as Nscale, backed by Nvidia, is pursuing a US stock market listing reportedly seeking to raise up to $3 billion at a valuation of around $35 billion (about £26 billion). Microsoft and Anthropic are reported to account for roughly 85% of Nscale's existing contracts, making the loss of Microsoft as the Loughton tenant significant for investor confidence ahead of the listing.
According to reporting on Nscale's listing plans, other AI infrastructure firms, including US cloud-computing company CoreWeave and Australian developer Firmus, have faced comparable setbacks linked to questions about data-centre demand and delivery timelines. Separately, investment bank TD Cowen reported in 2025 that Microsoft had cancelled roughly a couple of hundred megawatts of planned US datacentre leases, citing facility and power delays alongside a reassessment of capacity needs.
UK industry figures cited in trade reporting estimate that more than a quarter of UK data-centre capacity due in 2025 slipped because of grid delays, with over 100 UK projects said to be considering on-site gas generation while they wait for grid connections.
Questions
- Why did Microsoft pull out of the Essex AI datacentre project?
- UK Power Networks told developer Nscale it could not connect the Loughton, Essex site to the electricity grid until the early-to-mid 2030s, far later than the facility's planned opening, so Microsoft withdrew as anchor tenant.
- Where exactly is the datacentre, and who is building it?
- The site is in Loughton, Essex, and is being developed by British AI infrastructure company Nscale, which is backed by Nvidia.
- Does Nscale still plan to build the Loughton datacentre?
- Yes. Nscale says it remains committed to the site and is exploring alternative power options, including on-site generation and talks with fuel-cell maker Bloom Energy, as well as other UK expansion sites.
- Does this affect Microsoft's other deals with Nscale?
- According to Nscale, no — the company says its relationship with Microsoft on other contracts, including a facility in Norway, is unaffected and describes the Loughton issue as a regional grid problem.
- Is the UK grid delay unique to this one project?
- No. Trade reporting cited in coverage of this story estimates that more than a quarter of planned 2025 UK data-centre capacity was delayed by grid connection issues, with over 100 projects considering on-site gas generation as a workaround.
Sources
- AOL (PA Media) — Microsoft drops huge AI datacentre project in Essex over power supply concerns
- Yahoo Finance — Microsoft pulls out of UK data centre deal with Nscale, Telegraph reports
- Bricks & Bytes — Nscale Has £2bn, Microsoft and Nvidia. It Still Can't Get 90 Megawatts.
- The Next Web — Britain's flagship AI data centre can't get the power to switch on
- Capacity Media — UK government reportedly urged Nscale AI data centre approval
- SSBCrack News — Microsoft Withdraws from UK's Largest AI Datacentre Project Amid Power Supply Concerns
- Tech Insider — Microsoft Exits Nscale UK Data Deal: Grid Waits to 2030s
- The Register — Microsoft's drawback on datacenter investment may signal AI demand concerns
This piece was prepared with artificial intelligence and passed an automated source check before publication. If you see an error, ask for a correction. Request a correction or reply · How we make this
Related

TechnologyArticle
Data Centers: Why Power, Not Chips, Is the Real Bottleneck for AI Growth
Data centers are the physical buildings that store, process and move the data behind AI chatbots, cloud storage and streaming services. The sector has become a global flashpoint in October 2026 after Microsoft withdrew as anchor tenant from the UK's largest planned AI data center because the local power grid cannot supply it until the 2030s.

TechnologyArticle
How AI Cracked a 217-Year-Old Napoleon Military Cipher in Six Hours
An AI engineer at the cybersecurity firm SentinelOne used OpenAI's GPT-6 Astra model to decode a homophonic-substitution cipher that Napoleon Bonaparte's headquarters sent to General Auguste de Marmont in March 1809. Working from a single scanned image, the system transcribed, analyzed and solved the 217-year-old code in roughly six hours, a task that had defeated cryptographers for more than two centuries.

TechnologyArticle
How 6G Could Be Monetized: Sensing Data and Physical AI Services
Telecom operators and vendors say 6G's revenue will not come from raw speed, as 5G's did, but from selling network sensing data and low-latency AI services to robots, drones and other "physical AI" systems. Early versions of these services are already being tested on existing 5G and 5G-Advanced networks ahead of 6G's commercial arrival, which industry sources now target for 2029–2030.
TechnologyArticle
How AI Is Changing Weather Forecasting: GraphCast, AIFS and Canada's GEML
Artificial intelligence is now running alongside, and in some cases outperforming, traditional physics-based weather models at agencies including the European Centre for Medium-Range Weather Forecasts and Environment and Climate Change Canada. AI systems such as Google DeepMind's GraphCast and ECMWF's AIFS generate forecasts in seconds instead of hours, using far less computing energy, while official assessments say classic physics-based models still handle some extreme-weather details better.